Do You Need a Demolition Permit in San Antonio?
Yes. Inside the city limits, San Antonio requires a demolition permit before a building comes down. Development Services issues it. The city’s published fee schedule lists $75 for a residential structure. A single story commercial building is $100.
The permit fee is the small part. The reviews behind it set your schedule. Every demolition application goes to CPS Energy, the Office of Historic Preservation and tree preservation staff first.
This page is general information, not legal advice. Rules change, so check with Development Services before you set a date.
What does a San Antonio demolition permit cover?
The city’s demolition bulletin says the permit is required to remove an entire building from a site. Each building needs its own application. A house and a detached garage is two permits.
Partial work is handled another way. Interior and partial demolition ride along with a remodel permit or a residential repair permit.
Some work needs no demolition permit at all. The bulletin lists fences, playground equipment, above ground pools, sidewalks, driveways, decks and detached sheds under 300 square feet. An in ground pool is not on that list, so call the city before you break one out.
How much is a demolition permit in Texas?
There is no statewide demolition permit and no statewide fee. Texas leaves it to the city or the county, so the number moves with the address. Here is what the City of San Antonio publishes in its current development fee schedule.
| City of San Antonio fee | Amount |
|---|---|
| Residential demolition permit | $75.00 |
| Commercial demolition permit, single story | $100.00 |
| Commercial demolition permit, 2 to 3 stories | $200.00 |
| Commercial demolition permit, more than 3 stories | $650.00 |
| Demolition contractor city license, first time | $85.00 |
| Demolition contractor city license, renewal | $35.00 |
Fee schedules get revised, so price the current one. Review fees, a tree permit or a right of way permit can land on top.
Do you need a license to do demolition in Texas?
Not from the state. Texas does not license demolition contractors or excavation contractors. The state licensing agency covers trades like electricians and air conditioning contractors. Demolition is not on that list.
Cities fill the gap. San Antonio registers demolition contractors. The city’s bulletin says a commercial building needs a city registered demolition contractor to apply. So does a residential structure of two stories or more.
One story houses are the exception. A property owner may submit the application for a single story residential structure with proof of ownership.
What permits do I need to demolish a house?
Inside the city, the demolition permit is the main one. The pieces around it are what people miss. This is the usual split.
| Step | Who handles it |
|---|---|
| Close the CPS Energy account, ask for the meters to be pulled | Property owner |
| Stop the water and sewer account | Property owner |
| Asbestos survey by a licensed asbestos inspector, where it applies | Owner or contractor hires the inspector |
| Notarized letter authorizing the contractor to apply | Property owner |
| Application, site plan, photos of all four sides | Contractor, or the owner on a single story house |
| Tree affidavit, or a tree permit if a tree comes out | Applicant |
| CPS Energy, historic and tree reviews | The city and CPS Energy |
| Right of way permit within 5 feet of public right of way | Applicant, through Public Works |
| Six foot security fence for the whole job | Contractor or owner |
| Engineer’s letter for two stories or more, or a basement | A Texas licensed engineer |
| Texas 811 locate request before anything gets dug | Contractor |
Skipping the tree step is expensive. City code sets a $2,000 fine for tree work started before the permit.
What about asbestos before a teardown?
The Texas Department of State Health Services has to be notified before the demolition of a public building. That holds even when no asbestos is found. Notice has to be in at least 10 working days before the work starts. Working days, not calendar days.
The survey behind that notice is done by a licensed asbestos inspector. San Antonio adds its own layer. A site specific asbestos survey report is required with the application for commercial buildings. A city ordinance sets that, and Development Services enforces it.
Most single family homes sit outside the federal rule. The EPA asbestos rule covers buildings and facilities but excludes residential buildings with four or fewer dwelling units. A house taken down inside a larger commercial project can be treated differently, so ask early.
Why does a demolition permit take so long?
Two reviews set the pace. CPS Energy has to confirm the electric and gas are off. The city warns that a CPS Energy service removal work order can take 30 to 45 business days. The permit is not issued until CPS Energy says it is safe.
The Office of Historic Preservation reviews every demolition application in the city. It checks whether the building is historic, sits in a historic district, or falls under the deconstruction ordinance. The city says that review can take up to a month.
Older houses need that answer first. The deconstruction ordinance runs on build dates. Inside the city limits it covers residential structures up to eight units built on or before December 31, 1945. It also covers structures built on or before December 31, 1960 that are designated historic. Those get taken apart by a deconstruction contractor certified by the city, instead of pushed over. That changes the budget and the schedule on a house demolition.
Building and tree review is quicker. The city says those are done within 3 business days.
Do you need a permit outside the San Antonio city limits?
It depends on the county, and Texas counties have narrower authority than cities. In the unincorporated parts of Bexar County, building permits run through the Fire Marshal’s office. Single family dwellings are exempt. Other counties set their own rules, so call before you plan a teardown.
State and federal rules do not stop at the city line. Texas 811 is the clearest one. An excavator notifies the notification center no later than 48 hours before digging. Saturdays, Sundays and legal holidays do not count, and the notice cannot be more than 14 days ahead.
Where does the debris go?
To a permitted landfill. Texas environmental rules sort landfills by type. A Type IV unit takes brush, construction and demolition waste and rubbish. A Type I unit takes all types of municipal solid waste.
Clean concrete is usually kept separate, which is where concrete removal and the slab under the house come in. A commercial demolition adds one more document to the application. The city calls it a means and method letter, covering the timetable, the method and the equipment.
Start the paperwork before the machines
Utility disconnects, the asbestos survey and the historic review run on their own clock. The teardown itself is the short part. Get the paperwork moving and the machine work lands where you want it.
We take structures down across San Antonio and about 50 miles around the city, from our yard in Pleasanton. For teardown numbers, what a house demolition costs in Texas covers the published market ranges. Call (253) 606-9497 for a free estimate.